The distributed power station application process |
Distributed mainly approval documents:
1. The land use right (forms: transfer or lease)
2. Power grid licensing company
3. The development and reform commission for examination and approval for the record
Step 1: determine the land use right
1. Find the target land, determine the land owner or the jurisdiction of the administrative units.
2. The bureau of land and resources that nature of the land, barren hill slope, agricultural land (need to build greenhouses photovoltaic power station or complementary production), fish ponds and lakes (built yu light complementary distributed power plant)
3. Introspection, cities, villages and towns as investment projects, the specific land transfer as the land. For example (a
Leave to farmers rent; B. public resources to the corresponding administrative unit rent; C. has been third-party leased land rent to a third party) note: factory do 1 mw of basic roof is 1 square, do 1 mw power station need to 25 to 30 acres of ground
The second step: licensing the interconnection
1. The plan passed by the national development and reform commission, the electric power company issued according to the project design access scheme draft (the national electric power company issued by free). Got the license for the grid
Step 3: the national development and reform commission for the record project (currently distributed power plant installations provinces are gap is very big, so have to promote the strength of the larger)
1. To land, development and reform commission (NDRC) new energy functions with distributed power plant the application form, the corresponding complete;
2. According to land condition, combining the local development and reform commission (NDRC), issue the plan feasibility study report (preliminary), note: there are a lot of unit can write the work |
|